YD多速电机如何接线
YD多速电机如何接线。、电动机Y/Y2/Y3/YE3系列电动机的绕组引出线为6根。YD/YZD/YDT系列双速、三速及四速电动机根据不同绕组有可能为6/9/12根。
1. There are 6 lead-out wires of the motor windings for Y/Y2/Y3/YE3 series. The number of the lead-out
wires for the motor windings could be 6/9/12 depending on different windings types, for YD/YZD/YDT series
two-speed, three-speed and four-speed motors.
2、电动机的旋转方向从轴伸端视为顺时针方向,任意对调三相电源线中的两根,电动机可改变转向。
2. The rotation direction of the motor is clockwise (viewed from shaft extension end). Any swap between
two of the three-phase power lines can change the motor steering.
3、按照接线图接好电源线(YD/YZD/YDT系列电动机要按照接线图要求连接好引出线)。外接额定电压进行电动机空载试验。
注意:大极比S3(周期)工作制电动机空载试验时间不宜过长,观察电动机是否有异常现象,否则应迅速断电检查。
3. Connect the power lines in accordance with the wiring diagram(the lead-out wires of the YD / YZD / YDT
series motor should be connected in accordance with its wiring diagramm). Power the motor with rating
voltage the test it with no-load at first.
Note: For motors with S3 operating system, the no-load test should not last too long. Observing are there any abnormal phenomenas, otherwise you should cut off the power supply immediately and check the system.